developmentHigh priorityopen

Public market at 211 N. Broadway timeline extension

Green Bay

Summary

The On Broadway public market is nearly two years behind schedule after construction bids came in $4.4 million over estimate. The RDA extended the deadline to December 2027 while requiring the nonprofit to prove its financing by May 2026.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jan 13, 2026.

Impact analysis

💰Financial impact

No new city money — the city's existing commitments stay capped at about $2.08 million plus a $1 million state trust fund loan.

✅Who benefits

Downtown residents and visitors get a community public market; donors and nearby businesses benefit from an activated Broadway district.

⚠️Who could be affected

Taxpayers carry risk if the project fails again to hit its revised milestones.

Mentions & discussions (1)

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Green Bay

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.